2026-02-22 18:03 - Checkpoint

Verdict: Aligned Trigger: Phase boundary

Aligned:

  • T-001 to T-004 match Phase 1 scope (@config, slides scaffold, workspace/network/turbo integration).
  • T-005 and T-006 establish the planned layout and styling foundation for Slidev report rendering.
  • T-007 to T-010 deliver the expected composables and reusable components for data-driven slides.
  • Boundaries respected: NETWORK.yml and pnpm catalogs were updated, and no forbidden cross-framework coupling was introduced.
  • Non-goals respected: no replacement of @services/present and no dashboard embedding work.

Patterns:

  • Tasks are completed in phase order with dependency alignment.
  • Progress entries map each task to acceptance criteria and touched files clearly.
  • Implementation remains foundation-first before template and CLI phases.

Recommendations:

  • Start Phase 4 tasks T-011 to T-015 and validate templates against real report JSON, including sparse data edge cases.
  • Prioritize success criterion coverage in Phase 5 by proving pnpm slides -- dev --entity IONS --period 2026-02 end-to-end.
  • Keep smoke-testing @services/present during later migration/export phases to preserve coexistence guarantees.

2026-02-22 18:16 - Checkpoint

Verdict: Minor Deviation Trigger: Phase boundary

Aligned:

  • T-001 through T-017 are complete with matching task-state and progress evidence.
  • Execution stayed in planned order across Phase 1 to Phase 5.
  • Boundaries continue to be respected (@config remains framework-agnostic, workspace/network updates were applied, and present-service coexistence is preserved).
  • Template coverage and CLI/picker flows are implemented and validated end-to-end.

Deviations:

  • T-017 planned file scope listed only scripts/picker.ts, while implementation also touched dependency/catalog files to support prompt runtime.

Patterns:

  • Incremental validation is consistent (lint/type-check + Slidev build/dev smoke checks).
  • Progress logging remains detailed and acceptance-criteria aligned.

Recommendations:

  • Proceed to Phase 6 (T-018, T-019) and keep the @services/present regression smoke test explicit.
  • Capture export quality notes during T-020 and T-021 to support final PPTX/PDF recommendations.
  • Finalize with T-022 doc updates so architecture/state artifacts stay in sync with implementation.

2026-02-22 18:21 - Checkpoint

Verdict: Aligned Trigger: Session checkpoint

Aligned:

  • T-018, T-020, and T-021 were completed with validation runs and generated artifacts.
  • Task status fields were normalized to match acceptance/progress evidence.
  • Ask-first boundaries are respected by leaving T-019 and T-022 pending until approval.

Patterns:

  • Execution remains dependency-ordered and evidence-backed (commands + artifacts + progress entries).
  • Export workflow is stable across PDF, per-slide PDF, and PPTX formats.

Recommendations:

  • Get approval for T-019 and T-022 to unblock final completion.
  • After approval, run one final /plan.save completion checkpoint and close plan status.

2026-02-22 19:29 - Checkpoint

Verdict: Aligned Trigger: Plan completion

Aligned:

  • T-019 and T-022 completed after explicit approval for ask-first boundaries.
  • Present service regression command succeeded after color/theme sourcing migration.
  • Architecture and state docs now include @config and @services/slides with updated flow/port references.
  • Task tracker, progress log, and summary status are synchronized at 22/22 tasks.

Patterns:

  • Execution remained phase-ordered and evidence-backed through finalization.
  • Deviations were explicitly amended and documented when tooling constraints changed implementation details.

Recommendations:

  • Keep @services/present as PPTX fallback until business QA confirms Slidev PPTX parity.
  • Resolve open plan questions (font selection and scope of @config) before starting follow-up implementation plans.